Smart Grid Pilot Projects Under Execution in India (2013-2016)

Print Friendly

(Prev… – Page 5)

11.  HPSEB, Himachal Pradesh

Location:

Industrial town of KalaAmb

Project Summary:

The pilot project covers 650 consumers and having annual input energy of 533 MUs. The functionality of peak load management and outage management is proposed by implementing Automated Metering Infrastructure (AMI) for Industrial Consumers, Distribution Automation and Substation Automation and power quality management by deploying Power Quality meters at HT consumers.

hpseb-logo-296x300

Benefits:

–          Shifting peak load

–          Reduction in penalties

–          Reduction in outages

Key Facts

Project Type: Smart Grid Pilot in Power Distribution Sector
Total cost of project: Rs. 17.84 Cr
MoP Share: Rs. 8.92 Cr
Funding Programme: RAPDRP, Part-C
Project timeline: 15 months from the date of award of the contract
New Technology: High End Power Quality meters to be installed at HT consumers (Steel Mills), 1 each at 132, 33 & 11 KV consumers for capturing power quality data remotely for identifying decision on corrective actions in collaboration with consumers.
Website: http://www.hpseb.com/

12.  PSPCL, Punjab

Location:

Tech-II Sub-division, SAS Nagar

Project Summary:

The functionality of Peak Load Management is proposed by implementing Automated Metering Infrastructure (AMI) in the project area for 9818 residential and industrial consumers. The area has around 60 MU input energy.

Benefits:

–          Reduced AT&C Losses

–          Reduced Peak Load Consumption

–          Reduced Cost of Billing

Key Facts

Project Type: Smart Grid Pilot in Power Distribution Sector
Total cost of project: Rs. 10.11 Cr
MoP Share: Rs. 5.06 Cr
Funding Programme: RAPDRP, Part-C
Project timeline: 17 months from the date of award of the contract
New Technology: Outages are very frequent in PSPCL. It is proposed to implement Outage Management Systems (OMS) to increase network reliability by proactively monitoring the grid for potential problems using distribution analytics and alarming for notification.
Website: http://www.pspcl.in/

(Contd… – Page 2 | Page 3 | Page 4 | Page 5 | Page 6 | Page 7 | )

Facebook Comments

Comments

comments

VN:F [1.9.22_1171]
Rating: 8.3/10 (8 votes cast)
Smart Grid Pilot Projects Under Execution in India (2013-2016), 8.3 out of 10 based on 8 ratings

Pages: 1 2 3 4 5 6 7